Shortest Job First (exercise 14.5): \( n \) programs of durations \( t_i \), run one after the other, in the order that minimizes the average time of completion: by increasing duration, since moving the shortest program to the front of any order does not increase any time of completion; \( O( n \log n ) \). More...
#include "ADS/Contract.h"#include <algorithm>#include <cstddef>#include <numeric>#include <vector>#include "ADS/optimization/impl/ShortestJobFirst.tpp"Go to the source code of this file.
Namespaces | |
| namespace | ADS |
Functions | |
| template<class T> | |
| std::vector< std::size_t > | ADS::shortestJobFirst (const std::vector< T > &t) |
| the order of the programs, by increasing duration | |
| template<class T> | |
| T | ADS::totalCompletion (const std::vector< T > &t, const std::vector< std::size_t > &A) |
| the sum of the times of completion of the programs in the order \( A \), \( \sum_k ( t_{A[ 0 ]} + \cdots + t_{A[ k ]} ) \) | |
| template<class T, class W> | |
| std::vector< std::size_t > | ADS::smithOrder (const std::vector< T > &t, const std::vector< W > &w) |
| the order of the programs of times \( t \) and weights \( w \) of least weighted sum of the times of completion, by increasing \( t / w \) (Smith's rule) | |
| template<class T, class W> | |
| auto | ADS::weightedCompletion (const std::vector< T > &t, const std::vector< W > &w, const std::vector< std::size_t > &A) |
| the sum of \( w_i C_i \) in the order \( A \), \( C_i \) the time of completion of \( i \) | |
Shortest Job First (exercise 14.5): \( n \) programs of durations \( t_i \), run one after the other, in the order that minimizes the average time of completion: by increasing duration, since moving the shortest program to the front of any order does not increase any time of completion; \( O( n \log n ) \).
With the weights \( w_i \) of the programs (the probabilities of the files on a tape, read at the times of completion), the order of least weighted sum \( \sum_i w_i C_i \) of the times of completion \( C_i \) is Smith's rule, by increasing \( t_i / w_i \), compared as \( t_a w_b < t_b w_a \) (no division, and a program of weight 0 goes last): the exchange of two adjacent programs \( a \), \( b \) changes the sum by \( t_a w_b - t_b w_a \); \( O( n \log n ) \). With precedence constraints the problem is NP-hard in general, and solved by Lawler's merging of chains on series-parallel orders.
The contracts [see Contract.h]: the times are not negative, the order is by increasing time, and the order given to totalCompletion() has places of \( t \); the weights are not negative and no program has both time and weight 0, and the order of smithOrder() is by increasing \( t / w \). The operations are defined in ShortestJobFirst.tpp.